| Road name | Parish | Description | Traffic Management | Start Date | End Date | Contractor |
| Imberhorne Lane | East Grinstead | Lay new drinking water main and connect to existing main. | Multi-Way Signals. | 13-Jul-2015 | 31-Jul-2015 | South East Water |
| Imberhorne Lane | East Grinstead | New drinking water main and services and connections. | Road Closure northbound. | 23-Jul-2015 | 04-Sep-2015 | South East Water |
| West Hoathly Road | East Grinstead | Tree maintenance. | Two-Way Signals. | 05-Aug-2015 | 05-Aug-2015 | West Sussex Highways |
| West Street | East Grinstead | Connect to SGN gas main providing supply to new development. | Two-Way Signals. | 10-Aug-2015 | 14-Aug-2015 | GTC |