SGN Works at Imberhorne Lane – Update
29 June 2015
Please note: this news article is in our archive. Articles were correct at time of publication, but should not be relied on for accuracy after the passage of time.
SGN have revised their proposed completion date to 3/7/15. One week earlier than their original proposed end date of 10/7/15. WSCC have been working hard behind the scenes with SEW to establish if advantage of an early finish by SGN could be capitalised on, to reduce the impact of the overall project.
Unfortunately this has not been possible, which is due to the way that SEW have to complete their project, culminating with them working on London Road with traffic lights to connect, chlorinate and pressure test the new pipe. This activity will take place mid to late August 2015, as originally planned, when they will also be installing their new pipe.
Therefore, once SGN have completed their works on London Road, their traffic management will be removed and the traffic lights at the Imberhorne Lane junction will be restored to normal service.