WSCC grass cutting schedule

WSCC grass cutting schedule for highways verges:

https://www.westsussex.gov.uk/media/7712/urban_grass_schedule.pdf

Please note that it can take 4 weeks to get around the county so if there is a slippage from the proposed dates, please allow a reasonable leeway. If however the grass verges are not cut, please do liaise with your County Councillor to determine the reason:

  • Town (part) Herontye and Worsted – Cllr John O’Brien
  • Asplats, Baldwins (part) and Town (Part) – Cllr Liz Bennett
  • Imberhorne and Baldwins (part) – Cllr Heidi Brunsdon

Highways Upcoming and In-progress Works w/c 2nd May 2016

Road Parish Description Traffic management Start Date End Date Contractor
Beeching Way East Grinstead Install and remove temporary parapets to enable replacement. Overnight Road Closure. 06-May-2016 07-May-2016 West Sussex Highways
Birches Industrial Estate East Grinstead Maintenace on T-Mobile mast. Stop/Go Boards. 04-May-2016 06-May-2016 T-Mobile (UK) Limited
College Lane East Grinstead Install and remove temporary parapets to enable replacement. Two-Way Signals. 29-Mar-2016 06-May-2016 West Sussex Highways
Lewes Road East Grinstead Gas escape in progress. Two-Way Signals. 26-Apr-2016 05-May-2016 SGN
London Road East Grinstead Gully repair works. Multi-Way Signals. 27-Apr-2016 27-Apr-2016 West Sussex Highways
London Road East Grinstead Carriageway Patching (between county border and Lingfield Road). Multi-Way Signals. 11-May-2016 13-May-2016 West Sussex Highways
London Road East Grinstead New connection to water main. Lane Closure. 25-Apr-2016 29-Apr-2016 South East Water

Highways Upcoming and In-progress Works w/c 18th April 2016

Road Parish Description Traffic management Start Date End Date Contractor
Beeching Way East Grinstead Install and remove temporary parapets to enable replacement. Overnight Road Closure. 19-Apr-2016 21-Apr-2016 West Sussex Highways
College Lane East Grinstead Install and remove temporary parapets to enable replacement. Two-Way Signals. 29-Mar-2016 06-May-2016 West Sussex Highways
London Road East Grinstead Gully repair works. Multi-Way Signals. 27-Apr-2016 27-Apr-2016 West Sussex Highways
London Road East Grinstead New connection to water main. Lane Closure. 25-Apr-2016 29-Apr-2016 South East Water
Saint Hill Road East Grinstead Install gullies and new pipe in carriageway. Road Closure. 25-Apr-2016 26-Apr-2016 West Sussex Highways

Highways Upcoming and In-progress Works w/c 7th April 2016

Road Parish Description Traffic management Start Date End Date Contractor
Beeching Way East Grinstead Install and remove temporary parapets to enable replacement. Overnight Road Closure. 14-Apr-2016 16-Apr-2016 West Sussex Highways
Beeching Way East Grinstead Install lighting columns and removals, including jointing works. Lane Closure. 29-Mar-2016 13-Apr-2016 West Sussex Highways
College Lane East Grinstead Install and remove temporary parapets to enable replacement. Two-Way Signals. 29-Mar-2016 06-May-2016 West Sussex Highways
Lingfield Road East Grinstead Lay new gas service. Two-Way Signals. 04-Apr-2016 12-Apr-2016 SGN
Sandy Lane East Grinstead Leak on water communication pipe. Road Closure. 04-Apr-2016 06-Apr-2016 South East Water
West Hoathly Road East Grinstead Access overhead BT structure to repair service. Two-Way Signals. 11-Apr-2016 11-Apr-2016 BT

College Lane Bridge – Parapet Upgrade Works – revised start date

Further to my previous email regarding the parapet works at the bridge in College Lane, I wish to inform you that the revised start date will be Tuesday 29th March.

The works will last for approximately four weeks and traffic lights will be provided to control vehicles onto a single lane across the bridge. There will also be four night time closures of both the bridge and the road below to allow certain activities to be carried out safely. The evenings of these closures are currently programmed to be the 29th March and the 12th, 13th and 26th April, however, these times are subject to change depending on how the works progress.

The contractor is proposing to extend the normal daytime shifts in order to expedite the works, therefore, although all of the noisy activities (such as drilling etc.) will be carried out in the daytime, an occasional small level of noise disruption may be experienced at night.